Project Particulars
Project Particulars | |||
Contractor: | TNT | ||
Client: | Ethiopian Sugar Industry Group | ||
Consultant: Eng. | Acute Engineering PLC | ||
Project: | Sugar Corporation 4B+G+30 HQ Building Project | ||
Project Contractual Highlights | |||
Date of Contract Signature | March 18th, 2022 | ||
Commencement date | March 20th, 2023 | ||
Contract Duration | 1260 calendar days | ||
Date of Hand over of the site | March 29th, 2022 | ||
Completion date | August 31st,2026 | ||
Time for Contractor’s Mobilization | – |
Defect Liability Period | 1 year (12 months) |
Amount of Liquidated Damage | 0.1% of contract amount per day |
Minimum amount of payment Certificate | 50 Million ETB per month |
Type of Contract | Design Build |